Howdy GFC Fam,
First and foremost, we want to thank you for your patience and understanding as we navigate supply chain challenges and delays in delivering your accessories. Your support means the world to us, and we’re working tirelessly to get everything in your hands as soon as possible. Here’s the latest on what’s happening at GFC HQ:
Accessory Updates
Drip Rails
Our Drip Rails are moving steadily through production. A large batch is currently being powder-coated, and we’ve just received another shipment ready for the same process. Starting next week, shipping will resume for outstanding orders, and we aim to have all Drip Rail orders fulfilled within four weeks.
Camper Lighting Kits
Sometimes, even the best plans run into surprises. With the Chinese New Year extending lead times at our vendor’s factory, our usual four-week turnaround doubled unexpectedly. Despite this, we’re making headway:
-
By the end of January: 30 kits will ship out.
-
In February: Another 20 kits will be ready.
-
By mid April: A larger shipment will arrive in March allowing us to fulfill all remaining orders.
We know this delay is frustrating, but rest assured, brighter days (and lighting kits) are ahead.
TurboNap
TurboNap orders are in the final stretch! Our shipping partner has been steadily sending out 6 Standard kits daily, and XL TurboNaps will begin shipping next week thanks to an overnight shipment of covers. At our current pace, all outstanding TurboNap orders should be out the door in the next 2.5 weeks.
Headliners
As you all know by now, this has been a bit of an adventure. Vendor system changes and ice storms delayed our shipment of 42 rolls of fabric, but they’re finally en route. Once the fabric lands here in Montana, it will be split, laser-cut, and sent to our contract manufacturer, who can produce around 160 headliner kits per week.
-
This week: We’ve already shipped around 60 headliners and will continue to send out as many as possible as we receive this last batch from our contract manufacturer here in Montana.
-
In 14 days: We should get our first batch of headliners back from the rolls of fabric that are on their way. From there, we can continue boxing and shipping headliners at a consistent cadence.
We also want to address the missed deadlines for headliner submissions outlined in our December email. These delays have unfortunately pushed back production schedules and created additional challenges. To recap, the deadlines communicated in December were crucial to maintaining our timeline, and the missed deadlines have resulted in a delay in getting headliners shipped out by the date initially communicated. We appreciate your patience as we work diligently to resolve these issues and get headliners into your hands as soon as possible.
V2 Pro Tent Upgrades
We’re still on track to start shipping the new V2 Pro Tent upgrades in February. If you’re interested in installation at one of our partner shop locations or here in Montana, stay tuned—we’ll share more details soon.
Exciting News: The Leaderboard is Live!
We’re stoked to announce that our Leaderboard is officially up and running! This tool provides a transparent view of our progress, letting you track your order and see exactly where you stand. The leaderboard updates in real-time, so you’ll know when your accessories are on their way.
Click here to view the V2 Pro Accessories Leaderboard
Wrapping Up
We’re making strides every day, and we can’t thank you enough for being part of this journey. If you have questions or need support, our team is here to help. We’ll continue to send updates, share progress photos, and keep you informed every step of the way.
Thank you for your patience, your trust, and for being part of the GFC family.
Best,
Team GFC